How can solar and a battery cut your business electricity bill?

Solar can reduce imported electricity when generation meets your site's demand. A battery can move surplus energy to later hours, but adds costs and losses. DESNZ reports a non-domestic average of 24.51p/kWh including CCL for the second quarter of 2026 [S1]. Use your avoidable import rate, export terms and interval data to calculate the difference. Checked October 2026.

Last checked 17 October 2026

A small UK business can assess a fully funded solar and battery proposal to explore cutting electricity costs without paying upfront. Test avoided imports against actual demand; battery losses reduce usable energy [S3]. The fully funded model below is illustrative: request written benefit-sharing terms and ongoing costs before treating it as an offer. Start with cutting energy costs.

How does solar self-consumption reduce your bill?

Self-consumption means using your solar photovoltaic (PV) electricity on site. For your calculation, match generation with building and vehicle demand in each interval. Value the imports displaced at the charges actually avoided. Keep fixed charges outside that multiplication: NESO’s network residual structure includes daily fixed amounts [S6]. Before sizing generation, use the business energy saving guide to review your demand.

Start with the business electricity prices hub, which presents DESNZ consumption bands. The official tables distinguish prices including and excluding Climate Change Levy (CCL) [S2]. The opened DESNZ publication confirms an overall average of 24.51p/kWh including CCL for the second quarter of 2026 [S1]. Individual size-band spreadsheet cells could not be read in this check, so the example uses that verified average as a sensitivity input, not as your marginal rate.

Replace it with your site’s avoidable price before making a decision. Read standing charges and CCL with your accountant. Do not add the levy again to a price that already includes it.

What does a battery add, and what can it fail to recover?

A battery stores energy and releases it later; DESNZ notes that designs and efficiencies differ [S3]. Ask for usable kilowatt-hours (kWh), the energy capacity, and kilowatts (kW), the charge and discharge power. Both matter when checking whether stored solar can cover an evening load.

The government’s flexibility roadmap describes shifting demand and storing electricity for other periods [S5]. Your business case should test those functions against actual operating hours. Request a solar-only model before adding storage, so the battery’s extra contribution remains visible.

Peak shaving means limiting your import peak. Ask which bill item or connection constraint that changes. For time-of-use shifting, an assumed 1,000 kWh battery output at a 30p avoided rate is worth £300. At assumed 90% efficiency, input is 1,000 ÷ 0.9 = 1,111.1 kWh. At an assumed 15p charging rate it costs £166.67, leaving £133.33 before wear and other costs. These are assumptions, not market prices. Do not apply this value to energy already counted in a solar-storage calculation.

What could the annual benefit and payback look like?

This is an illustration, not a quote, for a daytime trading building with evening demand. All inputs below are assumptions except the DESNZ reference price [S1]. No charger sales are included, so driver prices and charging sessions are outside this calculation.

Input Assumption or reference
PV and annual generation 50 kW; 50,000 kWh, assumed yield
Battery 50 kWh usable; 25 kW discharge
Battery input and output each year 10,000 kWh in; 9,000 kWh out; 90% efficiency
Import reference 24.51p/kWh including CCL [S1]
Export receipt 5p/kWh, assumed eligible paid export
Combined capital £60,000–£80,000, assumed installed budget
Annual software and maintenance £1,000, including £300 allocated to storage
Funding shares Fully funded 10%; part funded 70%; self funded 100% of net benefit

The assumed capital budget excludes roof repairs and network upgrades. Annual figures exclude VAT, tax, financing, degradation, replacement and discounting. Obtain those project costs separately before relying on payback.

Use case Direct solar use Battery output Export Annual net benefit
Low 20,000 kWh 9,000 kWh 20,000 kWh £7,107.90
Mid 30,000 kWh 9,000 kWh 10,000 kWh £9,058.90
High 40,000 kWh 9,000 kWh 0 kWh £11,009.90

For mid use, avoided imports are (30,000 + 9,000) × £0.2451 = £9,558.90. Export is 10,000 × £0.05 = £500. Net benefit is £9,558.90 + £500 − £1,000 = £9,058.90. Apply the same formula to the other rows. Each case allocates the entire assumed generation between direct use, battery input and export.

How do fully funded, part funded and self funded compare?

These assumed benefit-sharing terms illustrate the funding choices; they are not available offers. For fully funded, the provider pays, owns and operates, and the host receives 10% of net benefit as an annual payment. Part funded assumes the host pays half the capital for 70% of net benefit. Self funded assumes full host ownership and costs. Define maintenance responsibility, billing and benefit ownership in the actual agreement.

Model and use Host capital Yearly net income or benefit Simple ROI Payback
Fully funded, low–high £0 £711–£1,101 income Not applicable Not applicable
Part funded, low £30,000–£40,000 £4,976 12.4–16.6% 6.0–8.0 years
Part funded, mid £30,000–£40,000 £6,341 15.9–21.1% 4.7–6.3 years
Part funded, high £30,000–£40,000 £7,707 19.3–25.7% 3.9–5.2 years
Self funded, low £60,000–£80,000 £7,108 8.9–11.8% 8.4–11.3 years
Self funded, mid £60,000–£80,000 £9,059 11.3–15.1% 6.6–8.8 years
Self funded, high £60,000–£80,000 £11,010 13.8–18.3% 5.4–7.3 years

Use unrounded benefit × share for host income. Simple ROI = annual net benefit ÷ host capital × 100; payback = host capital ÷ annual net benefit. Most self funded value is bill reduction, not cash sales.

Test the battery separately: 9,000 × £0.2451 − 10,000 × £0.05 − £300 = £1,405.90 extra yearly value over exporting that solar. An assumed £20,000 battery addition therefore has 7.0% simple ROI and 14.2-year payback, before ageing and replacement. A combined project can conceal a slower storage return.

What limits export income and the final decision?

The Smart Export Guarantee (SEG) covers eligible technologies, including qualifying solar installations up to 5 MW in Great Britain. Payments use export meter readings and contractual rates [S4]. Check metering, certification, storage treatment and permitted export before including income. No export receipt applies to energy used on site.

Review solar costs, battery costs and the commercial solar cost hub. If vehicles share the supply, use solar, battery and charging together and the charging cost tool.

What should you do next?

Take your interval demand, roof details and bill schedule to the site check, then get matched with an installer that covers your area.

Piggy Pineapple Ltd operates this referral service. We refer enquiries to installer partners and may be paid a fee. Our owner holds shares in at least one partner. Before sharing your details, we name the proposed partner and disclose any shareholding our owner holds in it. Read how we work.

Common questions

How can a small UK business cut its electricity costs without paying upfront?

Assess a fully funded proposal using interval demand and your avoidable import rate [S1], [S2]. Account for battery losses [S3] and written ongoing charges; the funded example here is illustrative, not an available offer.

Can annual solar generation establish that winter imports disappear?

No. Match generation and demand by interval, including winter operating hours. DESNZ describes storage as deferring energy use; an annual energy balance does not show enough stored energy for every later period [S3].

Is a standard export price set by the government?

No. Ofgem says SEG licensees set rates and contract terms, with a rate above zero and payments based on export readings. The 5p figure here is an assumption, not an available offer [S4].

How should you allow for battery ageing?

Request warranted usable capacity, throughput and efficiency, then rerun annual output and replacement costs. DESNZ distinguishes battery designs and efficiencies; its product-list criteria are not the specification of every battery [S3].

Can you use the national average as your exact avoided cost?

No. DESNZ's average describes prices paid across non-domestic users. Identify your size band, then use the charges your contract actually avoids when imports fall [S1] [S2].

Will solar remove the daily network residual charge?

Do not assume this. NESO describes residual charges allocated through bands as daily fixed amounts. Keep them in the baseline unless a separately verified change applies [S6].

Can fleet charging use the same solar energy as the building?

Allocate each kWh once in your interval model: to building demand, charging, storage input or export. Storage defers electricity use; it does not create a second allocation of generation [S3].

Ask about your site

Free for site owners. No obligation. We name the installer partner before we pass on any details.

Read our privacy notice

Sources

  1. Quarterly Energy Prices September 2026, Department for Energy Security and Net Zero,Last checked 17 October 2026
  2. Non-domestic electricity prices by size band, Department for Energy Security and Net Zero,Last checked 17 October 2026
  3. Battery Energy Storage, Department for Energy Security and Net Zero,Last checked 17 October 2026
  4. Smart Export Guarantee scheme overview, Ofgem,Last checked 17 October 2026
  5. Clean flexibility roadmap, Department for Energy Security and Net Zero,Last checked 17 October 2026
  6. Targeted Charging Review update, National Energy System Operator,Last checked 17 October 2026