Should your business install solar, batteries and EV charging together?

A combined project can serve vehicles and building demand, but the energy flows and funding contracts must agree. Eligible chargepoint installations can receive up to £500 per socket under the Workplace Charging Scheme [S3]. Start with your consumption and parking pattern, then test low, mid and high use. Solar generation alone does not establish charging income. Checked October 2026.

Last checked 16 October 2026

Why combine solar panels, battery storage and EV charging?

Consider a combined design when the same site needs vehicle energy, building electricity and control of peak demand. Ask the designer to show how each item contributes. A battery should solve a defined timing or power problem, rather than appear in the quote simply because solar and chargers are being installed.

Kilowatts, or kW, measure power. Kilowatt-hours, or kWh, measure energy. Solar photovoltaic panels, or PV, generate electricity; a battery stores it. The battery’s usable kWh and discharge kW answer different sizing questions. Put both in the specification, alongside the vehicles’ required departure energy.

DfT recorded 121,171 public EV chargers on 1 July 2026 [S4]. That gives national context, but your decision needs evidence of your own demand. Count arrivals, parking duration and opportunities to charge during solar hours. An office daytime fleet and a night-returning depot need different energy schedules.

How should you set up solar charging and battery controls?

Request an electrical diagram and an operating schedule covering sunny trading hours, dark evenings and vehicle charging overnight. Ask which controller decides where energy goes when several demands coincide. Include a test that checks whether the stationary battery is deliberately serving the vehicles or being reserved for a later building peak.

Use distinct energy lines in the model: direct solar use, solar stored and later delivered, grid purchases and exports. Assign each unit once. Our smart charging guide explains timetable comparisons. Read battery costs before paying for extra storage whose operational purpose has not been shown.

Which funding model fits your combined project?

Compare the whole arrangement, including access and energy rights. These descriptions explain the funding models; an actual proposal needs written terms.

Model Capital and operation Host return to compare
fully funded Provider pays, installs, owns and operates; host supplies the site Annual revenue share or rent
part funded Host and provider share capital; provider operates Host net income, ROI and payback
self funded Host buys the equipment and pays operating costs Whole project net income, ROI and payback

In a combined offer, ask who receives export payments and who sells solar electricity to the building. Request lease length, tariff-setting rights, maintenance, insurance, business rates allocation and exit terms. Ask your solicitor to check redevelopment, assignment and reinstatement obligations before signing.

What could the site earn, and how many years until payback?

This is an illustration, not a quote. All inputs below are assumptions, not sourced market prices or a prediction of solar yield. The model deliberately prices all vehicle energy as grid purchases. Solar supplies only a separate building load, so there is no double counting of charging margin and avoided imports.

Assumed input Value
Charging equipment 2 × 7 kW AC sockets; AC means alternating current
Sessions across the site per day Low 2 / mid 4 / high 6, over 365 days
Metered energy per session 20 kWh
Driver price / purchased electricity £0.45 / £0.20 per kWh, excluding VAT
Charger energy allowance Purchased energy = metered sales × 1.10 for losses
Software and charging maintenance £1,200 a year
Solar / battery 20 kW peak PV; 20 kWh usable storage with 10 kW output
Solar delivered to separate building load 10,000 kWh/year, after storage losses
Building import cost avoided £0.20/kWh; no export income included
Additional solar/battery maintenance £500 a year
Whole project capital £30,000–£40,000; major grid reinforcement excluded
fully funded host share 10% of gross charging sales; provider bears all costs
part funded host share and capital 50% of project net value; £15,000–£20,000
self funded host share and capital 100% of project net value; £30,000–£40,000

Annual sales energy E = sessions/day × 20 × 365. Charging margin = E × (£0.45 − 1.10 × £0.20) − £1,200. Building benefit = 10,000 × £0.20 − £500 = £1,500. Total annual net project value is the charging margin plus that building benefit. Here, net value includes avoided purchases; it is not all cash revenue.

Result Low use Mid use High use
Annual charging sales energy 14,600 kWh 29,200 kWh 43,800 kWh
fully funded host income/year £657 £1,314 £1,971
part funded host net/year £1,829 £3,508 £5,187
part funded simple ROI 9.1–12.2% 17.5–23.4% 25.9–34.6%
part funded payback 8.2–10.9 years 4.3–5.7 years 2.9–3.9 years
self funded host net/year £3,658 £7,016 £10,374
self funded simple ROI 9.1–12.2% 17.5–23.4% 25.9–34.6%
self funded payback 8.2–10.9 years 4.3–5.7 years 2.9–3.9 years

For the mid case, E = 29,200; net project value = 29,200 × £0.23 − £1,200 + £1,500 = £7,016. The part funded host gets half, £3,508. ROI = annual net ÷ host capital × 100. Payback = host capital ÷ annual net. The identical percentage ranges follow from assuming half the capital and half the net value.

The fully funded host receives E × £0.45 × 10%; it receives no building benefit in this assumed contract. In practice, document how any building benefit is credited or shared. The illustration excludes finance, tax, grants, degradation, replacements, insurance, rates and land costs. Add them before making a decision.

What does the site need before installation?

Ask the distribution network operator, or DNO, to assess the full connection proposal. G99 is an engineering recommendation for generation connections outside the qualifying G98 route [S1]. Charger demand needs its own assessment [S2]. See G98 versus G99.

Request a layout preserving accessible routes, deliveries and emergency access. Have the designer identify planning and landlord checks. HSE explains risk assessment duties for grid-scale battery systems; obtain a site-specific safety assessment rather than treating that guidance as a small-system layout specification [S5].

The Workplace Charging Scheme offers eligible installations up to £500 per socket, subject to its cost cap and eligibility rules, and runs until 31 March 2027 [S3]. Check eligibility before ordering. No grant is deducted in the illustration. Check tax treatment with your accountant.

HMRC lists qualifying new and unused EV charging equipment for first-year allowances [S6]. An allowance reduces taxable profits; it does not reimburse the equipment invoice. Keep any tax calculation separate from the operating example and have your accountant check eligibility.

What should you do next?

Collect your consumption records and vehicle timetable, then get matched with an installer that covers your area for a combined design and operating model.

Piggy Pineapple Ltd operates this advice and referral service. We refer enquiries to installer partners and may be paid a fee. Before sharing details, we name the proposed partner and disclose any shareholding the owner holds in it. Read how we work.

Common questions

Can overnight vehicle charging drain your stationary battery?

Ask the designer to test that operating mode explicitly. The ENA guide treats storage as part of the generating arrangement; require a control diagram showing when storage supplies the charging load [S1].

Does G99 replace an assessment of charger demand?

No. Generation connection requirements and EV demand assessment address different flows. Give the designer the combined solar, battery, charging and existing building loads [S1][S2].

Is the Workplace Charging Scheme a grant for the whole energy system?

No. Its support concerns eligible chargepoint purchase and installation. Do not subtract its award from solar or battery capital without a separately evidenced funding basis [S3].

Do national charger statistics prove your site will attract customers?

No. DfT's public network counts describe infrastructure, not your site's future sessions. Use parking observations, fleet records and a low-use sensitivity case to plan your project [S4].

Can charging equipment qualify for a capital allowance?

HMRC lists qualifying new and unused electric vehicle charging equipment for 100% first-year allowances. It is a deduction from taxable profits, not a cash grant; check with your accountant [S6].

Ask about your site

Free for site owners. No obligation. We name the installer partner before we pass on any details.

Read our privacy notice

Sources

  1. Distributed Generation Connection Guide - G98 and G99, Energy Networks Association,Last checked 16 October 2026
  2. Connecting electric vehicle chargepoints to the electricity network, UK Government,Last checked 16 October 2026
  3. Workplace Charging Scheme - guidance for installers, Office for Zero Emission Vehicles,Last checked 16 October 2026
  4. Public electric vehicle charging infrastructure statistics - 1 July 2026, Department for Transport,Last checked 16 October 2026
  5. Grid-scale battery energy storage systems, Health and Safety Executive,Last checked 16 October 2026
  6. Claim capital allowances - 100% first-year allowances, HMRC,Last checked 16 October 2026
Check your site