Should your Burnley workplace invest in EV charging?

Burnley had 107 public chargers on 1 July 2026 [S1]. Total and rapid provision per resident were below the North West and UK comparisons. For a workplace, staff attendance and charging access are more useful than population rates for sizing equipment. Test the low-use income and connection cost before committing capital or parking space. Checked October 2026.

Last checked 17 October 2026

What power and parking information should a Burnley workplace collect?

Begin with staff arrival times, shift changes and how long vehicles remain parked. For your own fleet, record return times and energy required before the next departure. Do not count internal fleet charging as sales to outside customers. The workplace sector guidance and fleet sector guidance help separate those requirements.

The distribution network operator (DNO) manages local electricity distribution assets. Electricity North West’s own service-area map includes Burnley [S3]. Confirm the exact premises, supply rating and maximum demand with your assessor. Its connection guidance says capacity is confirmed through formal application, not simply by viewing a map [S11].

Give the designer a parking layout showing deliveries, pedestrian routes and accessible bays. If charging spans a shift change, decide whether outgoing staff must move their vehicles and how the next users gain access. These arrangements determine how many sessions the equipment can actually serve.

How much charging provision is recorded in Burnley?

On 1 July 2026 Burnley North West UK
Public chargers per 100,000 people 107.8 112.2 174.9
Rapid chargers per 100,000 people 22.2 40 41.7

The council had 107 public chargers, including 22 rapid chargers [S1]. Comparisons are approximate:

Regional and UK rates are calculated from the supplied council rows. Population is inferred for each row as public chargers ÷ published rate × 100,000; summed counts are then divided by summed populations. The original rounded rates make these aggregates approximate. See the North West regional context.

Burnley’s supplied 2026 Q2 record has 1,889 plug-in vehicles, including 1,227 battery electric vehicles. Privately kept plug-ins account for 1,415 [S2]. These overlapping groups locate keepers, not workplace charging sessions. Survey staff before treating local adoption as a usage forecast.

The Blackpool visitor example shows why a different parking pattern needs different trading-day and session assumptions.

What does the council’s climate work tell a business?

Burnley’s climate strategy identifies on-street charging work in Kingsway, proposals for Padiham and participation in a taxi charging scheme [S4]. These are descriptions in the strategy, not confirmation that every proposed point is live today.

The council’s net zero actions page also describes its fleet transition and public car park charging rollout [S10]. That is relevant context when checking nearby alternatives. Neither document establishes funding eligibility for your private car park or proves spare capacity at your connection.

What could a shared workplace installation earn?

This is an illustration, not a quote for paid staff use. Power is measured in kilowatts (kW), while energy is measured in kilowatt hours (kWh). Alternating current (AC) is the equipment type modelled here.

Ten units at £1,200–£2,000 each, plus shared infrastructure of £3,000–£8,000, give £15,000–£28,000 [S8]. Add an assumed £2,000 for extra groundworks, cable runs and connection to reach £17,000–£30,000. A major supply upgrade remains additional. Check the commercial installation cost guide for quote components [S9].

Input Assumption for this illustration
Chargers 10 × 7 kW alternating-current (AC) chargers
Sessions per day across the site, low / mid / high 4 / 8 / 12
Trading days yearly / energy per session 250 / 16 kWh
Driver tariff / energy cost £0.40 / £0.22 per kWh
Annual software, maintenance and payment costs £1,200
Total capital / part funded host contribution £17,000–£30,000 / £8,500–£15,000
Host shares: fully funded / part funded / self funded 10% of sales / 50% of net / 100% of net
Annual result Low use Mid use High use
Energy sold, kWh 16,000 32,000 48,000
fully funded host income £640 £1,280 £1,920
part funded host net £840 £2,280 £3,720
self funded host net £1,680 £4,560 £7,440
Simple ROI, part funded and self funded 5.6–9.9% 15.2–26.8% 24.8–43.8%
Payback, part funded and self funded, years 10.1–17.9 3.7–6.6 2.3–4.0

Workings: annual energy = sessions × 250 × 16; sales = energy × £0.40; net = energy × (£0.40 − £0.22) − £1,200. For fully funded, a provider finances, installs, owns and operates the system and gives you 10% of sales. part funded assumes you pay half the capital for half the net. self funded allocates all investment and net to you.

Simple return on investment (ROI) = host annual net ÷ host capital × 100, and payback years = host capital ÷ host net. The equal proportional investment and income split makes the investment models’ ratios match. The example’s usage, tariff, costs and shares are assumptions, with VAT, grants, tax, business rates, financing, renewals and outages excluded. Change these in the income calculator.

Which obligations and support should be priced before signing?

WCS can support eligible installations with up to £500 per socket until 31 March 2027 [S5]. HMRC lists qualifying new, unused chargepoint equipment bought before April 2027 for first-year allowances; check with your accountant [S7]. Public-facing use needs review under the Public Charge Point Regulations 2023 [S6].

A fully funded offer needs clear provider maintenance and electricity obligations. For part funded, settle ownership and buy-out terms; for self funded, price ongoing operation. Ask your solicitor to review planning, landlord consent, liability, business rates allocation, lease length, redevelopment, exit and bay reinstatement.

Any solar or battery option should show its own capital and operating calculation against measured site demand, including when the vehicles need energy.

Next step

Prepare a staff usage survey and supply record, then get matched with an installer that covers your area.

Piggy Pineapple Ltd is the site’s operator. We may be paid a fee when we refer enquiries to installer partners. The owner holds shares in at least one partner. We identify the intended recipient and explain any shareholding in that business before passing your details on.

How many plug-in vehicles share each public charger here?

Burnley has 13.2 privately kept plug-in vehicles for every public charger, ranked 244 of 357 UK councils (1 = most vehicles per charger). The UK figure is 13.1; the middle council has 17.8.

That is fewer than most councils: the public network here is already relatively dense, so a new site needs a clear reason drivers will stop, such as dwell time or a customer offer.

Vehicles are counted where the keeper lives, and drivers with a driveway often charge at home. Use this as a first screen, not a forecast. Chargers as at 1 July 2026; vehicles as at 2026 Q2.

See every council ranked, or check your own site by postcode.

Common questions

Can the WCS cover a larger workplace rollout?

It supports up to 40 sockets across an eligible applicant's sites. Subtract earlier awards before working out the scope of a new application. [S5]

Does an available substation mean your project can connect?

No premises-specific capacity is confirmed until a formal application has been assessed, according to the network operator. Arrange that assessment before relying on an installation date. [S11]

How much do shared infrastructure costs add?

For five to ten 7 kW workplace units, the published benchmark adds £3,000–£8,000 shared infrastructure. Groundworks, cable runs and connection are extra. [S8]

How do capital allowances affect the budget?

A qualifying first-year allowance deducts eligible cost from taxable profits. It is not an equivalent cash grant. HMRC requires qualifying new, unused equipment; check with your accountant. [S7]

What should software and maintenance quotes specify?

Ask for separate recurring prices, included fault work and any payment fees. The commercial cost guide treats these as operating costs rather than one-off equipment costs. [S9]

Can a staff charger be opened to customers?

Assess the change in access before doing so. Regulation 3 distinguishes workplace users and customers buying goods or services; check the operating classification with your solicitor. [S6]

Ask about your site

Free for site owners. No obligation. We name the installer partner before we pass on any details.

Read our privacy notice

Sources

  1. Public EV chargers by local authority, EVCI0102, Department for Transport,Last checked 17 October 2026
  2. Vehicle licensing data, VEH0142, Department for Transport,Last checked 17 October 2026
  3. Distribution service-area map, Electricity North West,Last checked 17 October 2026
  4. Climate Change Strategy 2022–2026, Burnley Borough Council,Last checked 17 October 2026
  5. Workplace Charging Scheme installer guidance, Office for Zero Emission Vehicles,Last checked 17 October 2026
  6. Public Charge Point Regulations 2023, UK legislation,Last checked 17 October 2026
  7. First-year capital allowances, HM Revenue and Customs,Last checked 17 October 2026
  8. Commercial and workplace installation cost bands, Cost reference,Last checked 17 October 2026
  9. Commercial installation cost components, Cost reference,Last checked 17 October 2026
  10. Council net zero actions, Burnley Borough Council,Last checked 17 October 2026
  11. Connection capacity questions, Electricity North West,Last checked 17 October 2026
Check your site