Why do EVSE, device and connector counts differ?
EVSE means electric vehicle supply equipment: the part of a charging device that controls a session for one vehicle. A device is the physical unit; a connector is its plug or socket [S1]. Counting each gives different totals. Check the unit, reporting date and public-access scope before assessing charging around your business. Checked October 2026.
What is the difference between EVSE, a device and a connector?
Use the Department for Transport (DfT) definitions when reading its public charging tables. An electric vehicle (EV) can encounter several pieces of equipment at the same site:
| Term | What is being counted |
|---|---|
| Location | The site grouping charging equipment |
| Device | A physical unit containing charging equipment |
| EVSE | A session-controlling part serving a vehicle |
| Connector | A plug or socket connecting equipment to a vehicle |
A device can contain multiple EVSEs. An EVSE can offer alternative connectors that cannot be used together [S1]. Use the commercial charging guide to plan what your site needs.
Why can several plugs serve fewer vehicles?
Assume a hypothetical car park has a single cabinet with two EVSEs. Each EVSE offers two alternative connectors, but can supply only a single car at once.
The illustrative inventory is therefore one location, one device, two EVSEs and four connectors. It supports two sessions together under these assumed operating conditions. Counting the plugs would double that session count. This example applies DfT’s distinction; it is not a specification for a particular product [S1].
For a proposal at your site, request a diagram showing the cabinet, each EVSE, its connectors and the bays served. Ask the designer to demonstrate simultaneous operation before describing the installation’s capacity to customers.
Why did DfT’s headline counting unit change?
DfT made EVSE its primary metric in 2026. Its January release records 116,052 EV chargers and 87,796 devices on the same reporting date. These are alternative descriptions of the infrastructure, not separate quantities to add together [S2].
Read the table label before comparing periods. A move from devices to EVSE can change the apparent total without representing that many newly installed units. Keep the counting unit constant or show both series separately. Use regional charging data as a starting point, with its metric and date visible.
Does the count show how much charging your customers can use?
It does not establish delivered power or unrestricted access. Public charging guidance distinguishes physical equipment from the vehicle-level units inside it [S4]. Ask separately about shared power, accessible bays, opening times and out-of-service equipment.
DfT’s methodology describes a snapshot at the start of the reporting period. It excludes non-public domestic and workplace equipment and assigns locations to administrative areas [S3]. Your practical catchment may cross those boundaries. Record which area and access conditions you used before drawing a conclusion.
Pair the counts with public versus private charging, charger utilisation and the charging cost tool. A local inventory is an input to your assessment, not an income forecast.
What should you do next?
Visit the attract customers and staff hub and site check, then get matched with an installer that covers your area.
Piggy Pineapple Ltd operates this referral service. We refer enquiries to installer partners and may be paid a fee. Our owner holds shares in at least one partner. Before sharing your details, we name the partner and disclose any shareholding our owner holds in it.
Common questions
Is a charging location the same as a charger?
No. A location groups charging equipment at a site; it can contain multiple physical devices [S1]. Request equipment and session-capacity counts alongside the site count.
Where can you find the historical device series?
DfT retains charging-device statistics in table EVCI9001. Use that series when comparing device counts through time, rather than joining it to the EVSE series [S2].
Are staff-only workplace chargers included in public totals?
DfT excludes workplace equipment that is not publicly accessible [S3]. Confirm access arrangements before treating nearby workplace charging as an option for your customers.
Does a larger EVSE count prove your chargers would be underused?
No. DfT publishes an infrastructure snapshot, not your site's future demand [S3]. Check vehicle arrivals, opening hours and charging needs separately before preparing a utilisation assumption.
Can a hotel charger be public even on privately owned land?
Yes. Government guidance includes publicly accessible hotel car parks. Land ownership alone does not decide whether charging is public; check the operating arrangements with your solicitor [S4].
Ask about your site
Sources
- Electric vehicle charging infrastructure statistics: frequently asked questions, Department for Transport,Last checked 18 October 2026
- Electric vehicle public charging infrastructure statistics: January 2026, Department for Transport,Last checked 18 October 2026
- Electric vehicle public charging infrastructure statistics: Methodology note, Department for Transport,Last checked 18 October 2026
- Public Charge Point Regulations 2023 guidance, Office for Zero Emission Vehicles and Department for Transport,Last checked 18 October 2026