Should your business use solar electricity or export it?

Compare the import cost avoided by using solar with the payment available for exporting it. Eligible Great Britain solar installations up to 5 megawatts can investigate SEG export payments [S1]. Your contract and demand timing determine the result. Separate cash receipts from avoided purchases, deduct operating costs and compare funding terms using the same energy flows. Checked October 2026.

Last checked 16 October 2026

What is solar self-consumption, and how does it differ from export?

Self-consumption is solar electricity used at your premises. Export is electricity sent to the network. A kilowatt (kW) measures power; a kilowatt-hour (kWh) measures energy. Track the energy flows separately before assigning financial value. The same unit cannot replace a grid purchase and be sold as export at the same time.

Ask for time-matched consumption and generation calculations. PVGIS, the European Commission’s solar modelling tool, estimates production for a grid-connected system without battery storage [S2]. It does not by itself show your site’s electricity purchases or export income. Read solar sizing before accepting a fixed self-consumption percentage.

Is using solar electricity worth more than exporting it?

Compare your actual avoidable import unit cost with your available export rate. Where the former is higher, direct use has more value per unit. Keep standing charges and costs that do not change with consumption out of the avoided-unit calculation. Ask your supplier which components of your bill would actually change.

The Smart Export Guarantee, or SEG, offers eligible generators payments through participating suppliers. Rates and contract lengths are supplier-set [S1]. Obtain written terms for your business rather than using a domestic headline tariff. Explain uncertain future rates through sensitivity cases instead of extending today’s offer across the whole equipment life.

What could your site earn, and how long is the payback?

This is an illustration, not a quote. All costs, tariffs, shares, yield and operating patterns below are assumptions, not market benchmarks or partner offers. It isolates consumption overlap while holding generation constant. No grant, tax relief, borrowing cost or future replacement is included. Amounts exclude recoverable VAT; check your position with your accountant.

Assumption Value
Solar array and assumed annual yield 50 kWp; 900 kWh/kWp
Annual generation 50 × 900 = 45,000 kWh
Direct-use share, low / mid / high 30% / 60% / 90%
Avoided import price; export price £0.25/kWh; £0.06/kWh
Software and maintenance £600/year
Installed capital, self funded £40,000–£60,000
Host capital, part funded £20,000–£30,000
Host capital, fully funded £0
Host share of net value, fully / part / self funded 20% / 60% / 100%
Charger kW, sessions/day, kWh/session, driver price Not applicable; no charger included

For self funded, net value combines avoided purchases and export cash, less annual costs. For the hypothetical funded contracts, assume the provider sells direct-use solar to the host at £0.25/kWh, receives export receipts, deducts £600 and pays the host its stated share. The host therefore has no separate unit-price saving under those funded assumptions. This settlement structure is assumed solely to make the comparison reproducible. It is not a claim that funded solar contracts normally pay these shares.

Gross value = direct-use kWh × £0.25 + exported kWh × £0.06. Net value = gross value − £600. For the mid case: 27,000 × £0.25 + 18,000 × £0.06 − £600 = £7,230/year.

Annual result Low use Mid use High use
Direct-use energy, kWh 13,500 27,000 40,500
Exported energy, kWh 31,500 18,000 4,500
Gross value £5,265 £7,830 £10,395
Net value before host share £4,665 £7,230 £9,795
Fully funded host cash income £933 £1,446 £1,959
Part funded host net cash income £2,799 £4,338 £5,877
Self funded net annual benefit £4,665 £7,230 £9,795

Annual host result = net value × host share. Simple return on investment (ROI) = annual host result / host capital × 100. Simple payback = host capital / annual host result. Ranges below reflect the stated capital range; they are not confidence intervals.

Funding result Low use Mid use High use
Part funded ROI 9.3–14.0% 14.5–21.7% 19.6–29.4%
Part funded payback, years 7.1–10.7 4.6–6.9 3.4–5.1
Self funded ROI 7.8–11.7% 12.1–18.1% 16.3–24.5%
Self funded payback, years 8.6–12.9 5.5–8.3 4.1–6.1

Fully funded has no host capital to recover in this illustration; report annual cash income rather than an infinite ROI. Self funded income is not all cash: the mid case comprises £1,080 export receipts plus £6,750 avoided purchases, less £600 operating costs. Check solar payback for the wider appraisal questions.

Which funding model fits your site?

HMRC treats solar panel expenditure as special-rate expenditure [S3]. Check applicable relief with your accountant; the illustration excludes tax effects rather than assuming a particular claim.

Fully funded transfers capital and equipment operation to the provider, while you provide the agreed site rights. Part funded shares the capital and requires clear ownership and settlement terms. Self funded leaves you paying the capital and retaining the net result after costs. Compare written offers against the same energy model.

Ask how a power purchase agreement affects the price of solar used on site, export ownership and any host rent. Many commercial structures will differ from the illustration. Recalculate the whole host cash flow, including payments to the provider. Read funded versus owned solar.

Have your solicitor check roof rights, maintenance access, lease length, insurance, exit payments and removal. Ask who funds repairs and any business rates liability. Do not assume these costs disappear because someone else owns the equipment.

Should you add a battery before exporting surplus?

Model it as an additional investment. Compare useful stored output with foregone export income, storage losses and incremental costs. Ofgem’s storage guidance also requires attention to the origins and metering of exported electricity [S4]. Read battery tariff arbitrage before combining the calculations. Keep battery trading and solar export value separate so the same energy is counted once.

What should you do next?

Request interval demand data, a generation model, a business export offer and itemised funding terms.

Piggy Pineapple Ltd operates this referral service. We refer enquiries to installer partners and may be paid a fee. Our owner holds shares in at least one partner. Before sharing details, we name the proposed partner and disclose any shareholding the owner holds in it. Read how we work and get matched with an installer that covers your area.

Common questions

Must your export buyer also supply your electricity?

No. Ofgem says your SEG supplier can differ from your electricity supplier. Compare the export offer as its own contract and confirm the metering needed to support actual readings [S1].

Is there a single national business export rate?

No. SEG suppliers set their rates and contract terms, with the tariff above zero. Obtain an eligible business offer before assigning a price to exported electricity in your forecast [S1].

Does SEG cover Northern Ireland premises?

No. Ofgem specifies Great Britain for SEG installations. A Northern Ireland site should confirm local network, metering and electricity purchase arrangements before forecasting export income [S1].

Can grid-charged battery exports automatically receive SEG payments?

No. Ofgem's storage guidance distinguishes eligible generation from other exported electricity. Where the meter cannot distinguish those sources, the supplier is not obliged to pay for that mixed export [S4].

Are solar panels always treated as main-rate plant for tax?

No. HMRC designates solar panel expenditure as special-rate expenditure. Other reliefs may affect an actual claim. Keep tax outside the base illustration and check available allowances with your accountant [S3].

Ask about your site

Free for site owners. No obligation. We name the installer partner before we pass on any details.

Read our privacy notice

Sources

  1. Export payment eligibility and supplier terms, Ofgem,Last checked 16 October 2026
  2. Solar generation modelling without battery storage, European Commission Joint Research Centre,Last checked 16 October 2026
  3. Solar panel capital allowances treatment, HM Revenue and Customs,Last checked 16 October 2026
  4. Storage co-location and SEG metering guidance, Ofgem,Last checked 16 October 2026
Check your site